January 30, 2023
Production

Schedule Material Associations

Schedule

The schedule now takes material associations into account at the operational level, rather than at the job level. Previously, jobs would not start until all material had been received, regardless of where the operation requiring the material fell. This will allow for increased efficiency for jobs to move through production.